Energy & trade / Regulatory Outlook
Grid connections: readiness becomes part of a project’s value
An early place in a queue is different from a project that can secure a workable connection.
Position at publication: Reformed connection process.
What is going on
Ofgem set out its vision for reforming Great Britain’s electricity connections framework in September 2024. In April 2025 it approved the connections reform package known as TMO4+. This introduced a process built around whether projects are ready and needed, rather than relying on their original queue position alone.
The connection is the link allowing a generating or storage project to exchange power with the network. The detailed criteria and the offer for each project matter. Reform of the process does not promise that every proposed scheme will connect sooner.
Read the original material: Ofgem — September 2024 regulatory framework · Ofgem — April 2025 connections reform decision
How it affects businesses
For a developer, connection timing affects when a project can begin earning money. It also affects the usefulness of land rights, equipment orders and financing arrangements. A cheaper site can lose its advantage if the project cannot export electricity when expected.
The new approach makes evidence of progress commercially significant. A project’s value may depend on whether its permissions and development arrangements support the relevant connection criteria. A buyer cannot safely infer that value from the age of an application alone.
Faster access for some projects can improve the use of the network, but changing priorities also creates uncertainty for others. The business question is which commitments remain affordable if a connection changes, and which can sensibly wait until the position is clearer.
How law firms can advise
Energy and regulatory lawyers can examine the applicable connection rules, offers and routes for resolving disagreements. Property and planning teams can assess the rights and permissions needed to support the project.
Finance and construction lawyers can then compare those assumptions with loan conditions and equipment or building contracts. For instance, who bears a delay, and can the delivery timetable change? On an acquisition, these teams can investigate whether the connection position matches the seller’s description. The work brings several documents into one business picture; a promising network position does not itself fund or build the project.
Sources
Official sources checked on 19 October 2026. The business implications and examples of legal work are analysis based on this material.