Energy Transition / Briefing

Grid connections: why a place in the queue was no longer enough

A place in the grid queue is useful only if a project can meet the requirements to connect.

Retrospective: Ofgem’s April decision to enable reform, not later connection offers or project outcomes.

Evidence cut-off: 26 April 2025. Current firm-practice context and later confirming records are identified separately in the text and sources.

01 / What happened

What happened

On 15 April 2025, Ofgem, Great Britain's energy regulator, approved a package enabling reform of electricity connections. The approach introduced tests of whether projects were ready and needed, rather than relying simply on their place in a queue. Ofgem decision

Connections matter because a power project cannot earn its expected electricity income without a usable route to the network. The reform changed how access would be prioritised. It did not establish that every proposed project would receive its preferred connection date.

02 / Who it affects

Who it affects

The decision mattered to renewable-energy and storage developers, their investors and the network businesses arranging connections.

A project could have land, an attractive design and potential demand for its electricity while still facing a network delay. Money already spent on development would not produce operating income during that wait.

For an investor considering buying a project, a stated connection position could therefore affect value. The important question was what that position actually entitled the project to receive under the new process.

03 / The business decision

The business decision

For a developer, the choice was how much to spend advancing a project and assembling evidence before knowing its final position.

Progress could improve readiness and make the investment case more credible. It could also put more money at risk if the project did not meet the relevant criteria or obtained a less useful timetable.

For a buyer, relying on the seller's description of a queue position would be insufficient. The commercial case depended on the underlying rights, evidence and conditions attached to it.

Contracts could help allocate that uncertainty. A purchaser might connect part of the payment to a later milestone, while a seller might prefer certainty at completion. Neither approach creates network capacity, but it changes who loses money if expectations are not met.

04 / Why it matters and what to consider

Why it matters and what to consider

The reform illustrates how a regulatory process can change the value of work already done. An early application and a project capable of being built are not necessarily the same thing.

It also connects several timetables. Land arrangements, equipment orders and financing can all depend on when a project can start operating. A change in one date can leave costs continuing while expected revenue moves further away.

Sources and scope

Last-checked date retained from the prepared editorial draft: 18 October 2026. This is historical analysis, not an account of the position today.

  1. Ofgem decision on connections reform

    Ready-and-needed criteria; decision and methodology framework

    Source date/context: 2025-04-15

  2. Burges Salmon — current published practice context

    Present-day practice connection only; no historical mandate inferred

    Source date/context: Current page; checked 2026-10-18