Electricity reform: a cheap site can still be an expensive place to build

A project’s location affects connection timing and costs, not just the price of the site.

Retrospective: the April delivery plan and consultation. Proposed location-related reforms are not treated as final charges or guaranteed connection dates.

Evidence cut-off: 25 April 2026. Current firm-practice context and later confirming records are identified separately in the text and sources.

01 / What happened

What happened

On 21 April 2026, the government published a delivery plan for Reformed National Pricing, its programme for changing how Great Britain's electricity system works. It also consulted on ways to influence where new energy projects are built. Delivery plan Consultation

The programme followed the decision to retain a national wholesale electricity market. That did not mean location would cease to matter. The plan examined network charges, connections and strategic planning as ways of guiding investment.

02 / Who it affects

Who it affects

The development mattered to developers of generation and storage projects, investors funding them and businesses that need substantial amounts of electricity.

A site may have attractive land costs or good natural resources while being poorly connected to the network. Electricity has to reach the places that use it. A bottleneck can therefore affect the value of a project even when its equipment works exactly as designed.

The plan was relevant to investment decisions, but it did not supply a final answer for every location.

03 / The business decision

The business decision

For a developer choosing between sites, the business decision was how much weight to give current costs and possible future changes.

A lower land price could be outweighed by a later connection or higher network costs. A more expensive site nearer useful infrastructure could become competitive when the full cost and timing were included.

Waiting for policy detail could reduce uncertainty. It could also mean losing a site or delaying work already needed to establish whether a project was feasible. Moving immediately would commit money before all the future rules were known.

Those risks could also affect a sale. A buyer and seller might disagree about how much value to give a hoped-for connection date or a possible future charge. The transaction would need to distinguish a confirmed entitlement from an assumption in the financial forecast.

04 / Why it matters and what to consider

Why it matters and what to consider

The commercial lesson is that one national electricity price does not make every project location equally attractive. Land, networks, construction and timing still interact.

The useful assessment asks which costs are already established, which depend on the particular project and which remain exposed to policy decisions. A reform intended to improve the system as a whole need not benefit every individual site.

Sources and scope

Last-checked date retained from the prepared editorial draft: 18 October 2026. This is historical analysis, not an account of the position today.

  1. Reformed National Pricing delivery plan

    National market retained; planned roles of network charging, connections and strategic siting

    Source date/context: 2026-04-21

  2. Consultation on siting and investment levers

    Consultation launch, not a final decision; current closed status is later context

    Source date/context: 2026-04-21

  3. Dentons — current published practice context

    Present-day capability only; not evidence of a historical mandate

    Source date/context: Current page; checked 2026-10-18

  4. CMS — current published practice context

    Present-day capability only; not evidence of a historical mandate

    Source date/context: Current page; checked 2026-10-18

Corrections policy · Educational disclaimer